I have a large baselined schedule. I am discovering that after the schedule was created, a few tasks were deemed not needed. I would like to keep these tasks in the schedule for history purposes, but how do I note that this task is not needed? I thought about filling in the actual start and actual finish dates, but this gives the impression that work was done. I thought about deleting them, but this loses my history. Is there a setting to change, or what should I do about this problem? Thanks!!!