I’m considering starting to use MSP 2010 more for my business. One thing we currently have to do manually is track all of our consultants across different projects. We don’t have project server (and can’t afford the $40/person/month for the ones we’ve found!). We have lots of individual project plans, kept by different people in different locations, with some of the same resources. Can we use resources across individual project plans? We could keep the centralized resource list on box.net? Ultimately we want to.
-
[*]Have a master calendar for all projects
[*]See what projects a person is attached to in what roles and the overall schedule for that resource
[*]Evaluate utilization of each person against targets (30 billable hours per week, 5 internal project hours per week, etc)
[*]know who is a consultant’s backup and what is their capacity to step in and help