The Problem
I want to ensure that a duration for 9 hrs work remains as 1 day with 100% of 1 resource.
I did not alter the base calendar.
1 Create a new resource calendar for slaves. Alter working time to create a 9hr day.
2 Assign the calendar to the resource on the resource sheet
3 Create a task, specify work as 9 hrs , assign 1 slave resource 100%
Result
duration > 1 day or resource allocation > 100%
What am I doing wrong?
Surely I do not have to alter the base calendar.
Does it matter whether I specify the resource cal is based on a copy of standard or not?
Thank you in anticipation
Geof