    I want to create a report for each resource on my project showing all the tasks they should be working on with dates. How do I do this?

    Viewing 0 reply threads
    Author
    Replies
    • #1276793

      Some thoughts…..

      How many and kind of projects? How many tasks? Date ranges?

      What software is available ie. MS Excel, MS Project, QuickBase?

      • #1276860

        one project, 400 tasks with 15 resources, 6 months. excel, project, access, no QB

        • #1278894

          Rob Gill’s book “VBA Programming for Microsoft Office Project” has the answer on page 281. The book is worth the price and you get to download all of the code as a bonus.

          Norm

    Viewing 0 reply threads
    Reply To: report project data for each resource

    You can use BBCodes to format your content.
    Your account can't use all available BBCodes, they will be stripped before saving.

    Your information: