The attached is a part of my first project. I am obviously not understanding something. I have reduced it to only the first five tasks to isolate the problem.
If I set the “Max. Units” for Buyer to anything less than 100% The resource goes red and recommends leveling. However leveling does not work and states that the over allocation can not be resolved.
The buyer can only spend 20% of his time on a given project.
I do not understand the problem?