    Suppose some tasks such as internal affair investigation are hidden, how would the total project cost is calculated?
    Will the costs of all hidden tasks be excluded?
    Armstrong

    Viewing 0 reply threads
    Author
    Replies
    • #1160690

      The Total Project Cost in the Project Statistics dialog box will remain the same if you filter the task list to exclued tasks by criteria, or if you expand or collapse the task list to hide tasks by levels.

      • #1160717

        The Total Project Cost in the Project Statistics dialog box will remain the same if you filter the task list to exclued tasks by criteria, or if you expand or collapse the task list to hide tasks by levels.

        Hi csimms,
        Thanks for your very generous advice. Perhaps a plausible solution would be a subproject consisting of confidential tasks.
        Armstrong

    Viewing 0 reply threads
    Reply To: Impact of Filtering on Cost Calculations

    You can use BBCodes to format your content.
    Your account can't use all available BBCodes, they will be stripped before saving.

    Your information: