    Hi,
    I want a field to show planned hours per task as of Status Date. I can use the Work field but that gives me the total hours per task. I want to see how many hours I planned as of the current date. Meaning, if I have a 4 days task, my work field will show 32 hours (8 hours/day x 4 days). I’m on day 2, I want a field to show me that I should have 16 hours of planned work. Then I can compare what my actual work is per day.

    Thanks,
    Deb

    Viewing 0 reply threads
    Author
    Replies
    • #1160695

      I used the Task Usage View to look at what you are wanting to display. I added the field called Remaining Work to the Task Usage Table. If your plan is updated as to what is complete it should show what you are looking for.

    Viewing 0 reply threads
    Reply To: How to show planned hours per task as of Status Date

    You can use BBCodes to format your content.
    Your account can't use all available BBCodes, they will be stripped before saving.

    Your information: