• How to show extended durations? (XP)

    Home » Forums » AskWoody support » Productivity software by function » Other MS apps » How to show extended durations? (XP)

    Author
    Topic
    #394931

    Hi,

    We cannot specify a project duration of greater than 100%. But what if a project extends beyond the expected duration? How can we show this project was extended in MSProjectXP?

    m.q.

    Viewing 1 reply thread
    Author
    Replies
    • #731468

      mq:

      You should save WITH a baseline before entering actual figures. If a project extends beyond the estimated duration, the difference can be viewed using the Varience table (View/Table/Varience).
      (One way of entering actuals is to use the Tracking table.)

      Tony.

    • #731469

      mq:

      You should save WITH a baseline before entering actual figures. If a project extends beyond the estimated duration, the difference can be viewed using the Varience table (View/Table/Varience).
      (One way of entering actuals is to use the Tracking table.)

      Tony.

    Viewing 1 reply thread