    I want to create a custom XL or HTML report out of my MS Project schedule plan that looks like the Resource Usage view – i.e. having the following as fields:

    1. Resource Name
    2. Work (Baseline/Actual/Work)
    3. Month-wise or week wise breakup of effort.

    Doing this manually is quite cumbersome. Would one need a macro for this? Is there one already written for such a requirement? I would be very grateful if somebody could help me on this.

    Thanks

    Pallav

    Viewing 0 reply threads
    Author
    Replies
    • #1155288

      Please respond, even if its a no. For now, I am copying and pasting the information into an XL and outlining it to give it a Resource Usage view feel. Can’t do that for very large plans (the one I am handling is a 40K hours plan, so its big in anycase). My stakeholders need ETC and actuals forecasting done month-wise using the plan, so have to use this approach.

      Thank you in advance,

      Pallav

      • #1155291

        I apologize for the lack of replies, but please be patient. The Project forum isn’t very busy, so our Project experts don’t look at it every day – they only check in once in a while to see if there are new questions.

    Viewing 0 reply threads
    Reply To: Extracting Report from MS Project 2003 with timeline information

    You can use BBCodes to format your content.
    Your account can't use all available BBCodes, they will be stripped before saving.

    Your information: