Good afternoon
Does MS Project always display the duration according to the base calendar?
A calendar is modified for a resource to show a 10hr working day and named labourers.
A resource, labourer, is assigned the calendar labourers.
A task is created with 10 hrs work and assigned 100% of a labourer.
Work is fixed
Result
The duration is reported as 1.25 days
The Gantt spans 1 day. (Modifying the time line display to display days and hrs verifies this.)
So is the duration calculation always based on the base calendar?
What must I do to show a duration of 1 day?
Thank you in anticipation.
Regards
Geof