    I have a consolidated plan consisting of 8 different plans & there are dependencies within the plans. Where it shows tasks from other plans in gray, it shows the amount of work & duration but it doesn’t add up these numbers for the summary tasks. Is there a way to show this?

    Viewing 0 reply threads
    Author
    Replies
    • #1071711

      The gray tasks are linked tasks in subprojects. If you have a consolidated plan you should not be seeing any gray tasks. The gray tasks should be visible in the individual subprojects only. If you have brought all of the projects into a single consolidated plan and you have used project summary tasks you should be seeing totals for work and duration. I am not sure where you are looking at Work totals. I added the work column to one of my consolidated plans to the task entry table and I am getting totals. If you have linked summary tasks to summary tasks and you are looking in the subprojects you will only get a path to the linked tasks.

      Carla

      • #1071719

        Carla,

        Thanks for the answer. You are correct, I have the task within the subprojects of which some are liked to other tasks of another sub-project. That’s working fine. What the PM is looking for is when they see a list of tasks under the summary task that includes linked tasks from other sub-projects (Grey) that the total days for all of the tasks under that summary total up for duration & work, I am not sure if this can happen.

        Danny

        • #1071749

          HI Danny,

          I see what you are looking for. Only thing I would know to do is to consolidate all the projects into a single window by making a single master project file, then the overall picture of summary groupings is easier to read. This is probably a lot of detail so you might try collapsing some of the detail in the master project.

          Carla

          • #1071769

            Thanks Carla, unable to do that as each project mgr wants their own plan incorporating workstream work. Thanks anyway.

    Viewing 0 reply threads
    Reply To: Consolidated 2003 Plan (2003)

    You can use BBCodes to format your content.
    Your account can't use all available BBCodes, they will be stripped before saving.

    Your information: