• Change hours on calendar

    Author
    Topic
    #461267

    We are trying to create and use a calendar with work hours of 7:00 AM to 6:00 PM for 11 hour days and 55 hour week. We have been able to create the calendar and assign it to a project and its tasks. We set the time line to be days and hours. We think that we have set all the places where the calendar needs to be selected, but still when we enter the first task of 2 hours, it starts at 8:00 AM instead of 7.

    Where are all the selections for the calendar or is there something else that we are missing?

    Viewing 1 reply thread
    Author
    Replies
    • #1171151

      Try going to Project ==> Project Information in the toolbar and in the Project Information dialog box assign the calendar you created with the eleven hour days as the base calendar for the project. Additionally check Tools ==> Options and on the Calendar tab make sure the settings synchronize with the base calendar you assigned.

      Carla

    • #1171202

      Thanks for the reply, Carla.

      I’m getting closer to what we want. We found that we needed to define the calendar for the non-working time for the Timescale to have the Gantt start at 7:00 AM. So the Gantt looks correct, but when we put in the first task it still starts at 8:00 AM.

      So here are the places we put the defined calendar:
      Project menu, Project Information, Calendar, Hourly
      Tools menu, Option, Calendar, daily and weekly hours set to default of the Hourly calendar
      Format menu, Timescale, Non-working time, Calendar, Hourly
      Task Information, Calendar, Hourly

      There must be some place where the calendar must be selected that we are still missing. We hope someone can tell us where that is.

      Thanks again, Barbara

      • #1179864

        I’m having a similar problem that I just came here for although I’m on Project 2007. I want to assign one resource to be available no more than 1/2 time. This can be between 8 and 5 but never available for more than 4 hours per day. So I created a 1/2 time calendar and assigned it to him. This has no affect on the leveling. He still shows the 8hpd as before. Any ideas?

        Bryan

        Thanks for the reply, Carla.

        I’m getting closer to what we want. We found that we needed to define the calendar for the non-working time for the Timescale to have the Gantt start at 7:00 AM. So the Gantt looks correct, but when we put in the first task it still starts at 8:00 AM.

        So here are the places we put the defined calendar:
        Project menu, Project Information, Calendar, Hourly
        Tools menu, Option, Calendar, daily and weekly hours set to default of the Hourly calendar
        Format menu, Timescale, Non-working time, Calendar, Hourly
        Task Information, Calendar, Hourly

        There must be some place where the calendar must be selected that we are still missing. We hope someone can tell us where that is.

        Thanks again, Barbara

    Viewing 1 reply thread
    Reply To: Change hours on calendar

    You can use BBCodes to format your content.
    Your account can't use all available BBCodes, they will be stripped before saving.

    Your information: