    My task is 100% completed, my actuals of $5000 in cost view are shown in Earned Value view under ACWP as $2500? Anybody know why?

    confused

    Viewing 0 reply threads
    Author
    Replies
    • #535124

      do you have a status date set in Project Information (on the projet menu)?

      • #535214

        hairout
        Roberta,
        Thanks for your response. Yes, I do have a status date set for the project. If I replace the actual cost number with a fake number, then re-input the correct number, it sometimes works okay. ACWP will then reflect the actual cost figures.Go figure. confused